BY CONTINUING TO USE THIS SITE, YOU ARE AGREEING TO OUR USE OF COOKIES. REVIEW OUR
COOKIE NOTICE

Register with us today

and in less than 60 seconds continue your access to:Latest news headlinesAnalytical topics and featuresCommodities videos, podcast & blogsSample market prices & dataSpecial reportsSubscriber notes & daily commodity email alerts

Already have an account?

Log in to register

Forgot Password

Please Note: Platts Market Center subscribers can only reset passwords via the Platts Market Center

Enter your Email ID below and we will send you an email with your password.


  • Email Address* Please enter email address.

If you are a premium subscriber, we are unable to send you your password for security reasons. Please contact the Client Services team.

If you are a Platts Market Center subscriber, to reset your password go to the Platts Market Center to reset your password.

In this list
Coal

Boiler damage delays Germany's 1.1 GW Datteln 4 coal plant to 2020

Bunker Fuel | Containers | Dry Freight | Marine Fuels | Tankers

How will shipping deal with higher fuel costs from IMO 2020?

Coal

Platts Global Coal Alert

Oil | Refined Products | Fuel Oil | Shipping | Dry Freight | Marine Fuels | Tankers

Mediterranean Bunker Fuel Conference, 8th Annual

Coal

Two reported Central Appalachia thermal coal deals push prices down

Boiler damage delays Germany's 1.1 GW Datteln 4 coal plant to 2020

Highlights


1.1 GW coal plant delayed two years

Boiler damage caused by testing

Q1 sales up, earnings down

London — Commissioning of Uniper's Datteln 4 coal fired power plant in Germany has been pushed back to summer 2020, the generator said Tuesday in its first-quarter results statement.

Not registered?

Receive daily email alerts, subscriber notes & personalize your experience.

Register Now

Commercial operation of the 1.1-GW plant, the only coal-fired power station in construction in Western Europe, was due to commence in Q4 2019, but initial testing of the plant in 2017 resulted in damage to the boiler in conjunction with the use of T24 steel.

The damage has since been under review, Uniper said, and initial findings "indicate that the boiler walls will have to be replaced to remedy the damage."

"This will delay the plant's planned commissioning, which will now presumably take place in the summer of 2020," it said.



A non-operating impairment charge of Eur270 million ($322 million) was recognized for the power station in Q1 2018.

A 30% year on year increase in Q1 European Generation sales to Eur2.9 billion was supported by improved hydroelectric conditions at the beginning of the year in Sweden and Germany, Uniper said.

Global Commodity sales were down 2% to Eur21.55 billion, with low temperatures in the second half of the quarter leading to increased demand for gas products, triggering "extreme price fluctuations at individual gas trading points," it said.

Adjusted earnings from European Generation fell 18% to Eur186 million, while that for Global Commodities fell 42% to Eur134 million.

Reduced earnings in generation were due to lower power prices from fossil-fired generation "and lower prices for nuclear and hydro generation volumes that had been hedged in the past," Uniper said.

Decommissioning of the Maasvlakte 1 and 2 coal units in the Netherlands, and the Oskarshamn 1 nuclear plant in Sweden, had additional negative impacts on earnings, it said.

--Henry Edwardes-Evans, henry.edwardes-evans@spglobal.com