Analysis: MISO to see 1.7 GW of renewables capacity come online by end of 2019: report

Commodities | Energy | Electric Power | Renewables | Natural Gas

Hydrogen: Beyond the Hype

Electric Power | Electricity | Energy | Energy Transition

European Long-Term Power Forecast

Energy | Oil | Energy Transition

APPEC 2023

Energy | Electric Power | Natural Gas | Oil | Nuclear | Crude Oil

FEATURE: Namibia seeks to pacify booming oil sector after fiscal terms confusion

Energy | Energy Transition | Petrochemicals | Oil | Coal | Natural Gas | Agriculture | Electric Power | Hydrogen | Emissions | Carbon | Polymers | LPG | Refined Products | Aromatics | Fuel Oil | Jet Fuel | Gasoline | Crude Oil | Biofuels | Renewables | Electricity

Insight Conversation: Saif Humaid al Falasi, ENOC Group

For full access to real-time updates, breaking news, analysis, pricing and data visualization subscribe today.

Subscribe Now

Analysis: MISO to see 1.7 GW of renewables capacity come online by end of 2019: report

Highlights

Likely to lower LMPs: analyst

1.4 GW postponed to 2020, 2021

  • Author
  • Mark Watson
  • Editor
  • Keiron Greenhalgh
  • Commodity
  • Electric Power
  • Topic
  • Energy Transition Environment and Sustainability

Renewable generation totaling 1.7 GW under construction in the Midcontinent Independent System Operator footprint is now slated for completion by the end of 2019, but 1.4 GW that previously had an in-service date in 2019 will now be delivered in 2020 or 2021, according to a report released Monday.

Not registered?

Receive daily email alerts, subscriber notes & personalize your experience.

Register Now

The additional wind generation is likely to put pressure on power prices, particularly in the wind-heavy MISO North region, where transmission constraints may be contributing to construction completion delays, an analyst said.

The grid operator's latest Generation Interconnection Queue report indicates 1,264 MW of generation that has come online so far in 2019 in MISO, led by Entergy's 904-MW (summer capacity) natural gas-fired, combined-cycle plant in St. Charles Parish, Louisiana.

But all except 55 MW of the generation under construction and has a negotiated in-service date in 2019 is wind powered. The remaining 55 MW is a hydroelectricity project in Iowa.

"Winter and summer, it should have a pronounced effect of lowering average [locational marginal] prices, especially for MISO North," Campbell Faulkner, senior vice president and chief data analyst at OTC Global Holdings, an interdealer commodities broker.

"Next summer it could cause some instability in dispatch, but the effect will be significantly smaller" than what would occur in the Electric Reliability Council of Texas, where the wind fleet makes up a much larger proportion of the generation mix, Faulkner said.

According to a MISO corporate fact sheet released in June, the grid operator has about 175,528 MW of capacity and a historic summer peakload of 127,125 MW. MISO's natural gas-fired fleet makes up 43% of that total, followed by coal with 32%, wind with about 11%, nuclear with about 8%, and others, including other types of renewables, making up the remainder.

In ERCOT, the wind fleet makes up 23.4% of total capacity, which is led by natural gas at 52.4%, and where coal makes up less than 16% and nuclear makes up about 5.4%.

This past summer in ERCOT, heat waves coincided with falling wind output in mid-August and early September, causing real-time locational marginal prices to spike to quadruple-digit levels during these periods and Energy Emergency Alerts to be declared on two days.

1.4 GW POSTPONED

When it comes to the postponed in-service dates for 1.4 GW of generation under construction, which MISO in September listed as having 2019 in-service dates, Faulkner attributed the delays to transmission constraints.

"MISO in the north is very capacity constrained," Faulkner said Monday. "It has been an ongoing issue since MISO began the massive build out of wind two decades ago. Overall, MISO has problems wheeling power to where it's needed from the rural generating regions."

Matthew Cordaro, a former MISO president and CEO who now resides in New York, also attributed the postponements to "overly optimistic" timelines presented by developers.

"One reason for this is developers in the beginning try to make their projects appear more attractive to potential financiers and also quite simply they overlook the many pitfalls that are out there," Cordaro said Monday. "This has been the case ever since the independent power alternative emerged in the evolution of deregulation."

MISO generation projects with 2019 in-service dates
Currently in service
State Type Capacity (MW)
Indiana Solar 17
Iowa Wind 90
Louisiana Natural gas 904
Under construction
Illinois Wind 150
Indiana Wind 400
Iowa Hydro 55
Iowa Wind 400
Louisiana Natural gas 933.8
Michigan Wind 80
Minnesota Wind 200
South Dakota Wind 400
In service date postponed since last report
Until 2020
Illinois Wind 202
Indiana Wind 503.6
Minnesota Wind 150
Until 2021
Indiana Solar 175
Iowa Solar 100
Minnesota Solar 50
Note: Summer capacity is listed for hydro and natural gas. Nameplate capacity is listed for solar and wind.
Source: Midcontinent Independent System Operator

-- Mark Watson, markham.watson@spglobal.com

-- Edited by Keiron Greenhalgh, newsdesk@spglobal.com