In this list
Electric Power

Generation at Finland's Olkiluoto-3 reactor delayed 11 months to Feb. 2022

Oil | Natural Gas (European) | Natural Gas | LNG | Renewables | Emissions | Energy Transition | Nuclear | Electric Power Risk | Electric Power | Coal | Energy | Electricity

Europe Energy Price Crisis

Electric Power | Electricity | Energy | Energy Transition

European Long-Term Power Forecast

Energy | Oil | Energy Transition

APPEC 2023

Energy | Energy Transition | Electric Power | Emissions | Electricity | Renewables

US Energy Secretary Granholm backs reforms to speed permitting process, touts industrial policy shift

Metals | Energy | Coal | Electric Power | Steel Raw Materials | Steel | Non-Ferrous | Electricity

Back in action: European mills restart idled blast furnaces on higher flat steel prices

For full access to real-time updates, breaking news, analysis, pricing and data visualization subscribe today.

Subscribe Now

Generation at Finland's Olkiluoto-3 reactor delayed 11 months to Feb. 2022

Highlights

1.6 GW EPR fuel loading March 2021

Grid connection Oct. 2021

Commercial operation Feb. 2022

  • Author
  • Henry Edwardes-Evans
  • Editor
  • Norazlina Jumaat
  • Commodity
  • Electric Power

London — Regular electricity generation at Finland's 1.6 GW Olkiluoto-3 nuclear power plant is to begin in Feb. 2022, 11 months behind the most recent schedule, project owner Teollisuuden Voima Oyj, or TVO, said Aug. 28.

Not registered?

Receive daily email alerts, subscriber notes & personalize your experience.

Register Now

The reactor is already over 12 years behind schedule and three times over its original Eur3.2 billion ($3.55 billion) budget. The EPR unit was originally scheduled to begin commercial operations in May 2009.

"The project schedule has been delayed by slow-moving system tests, technical problems identified in the tests, and an increase in the number of maintenance tasks due to project delays. A lack of necessary spare parts has also taken time," TVO said, referencing an updated schedule from plant supplier Areva-Siemens.

According to the new schedule, fuel will now be loaded in March 2021, the unit connected to the grid in Oct. 2021 and regular electricity generation starts in Feb. 2022.

"Of approximately 3,000 commissioning tests, only a few dozen remain," TVO's OL3 project director Jouni Silvennoinen said.

From first grid connection in Oct. 2021, the plant is schedule to produce between 1 TWh and 3 TWh at varying capacities ahead of commercial operations.