S&P Global Offerings
Featured Topics
Featured Products
Events
S&P Global Offerings
Featured Topics
Featured Products
Events
S&P Global Offerings
Featured Topics
Featured Products
Events
S&P Global Offerings
Featured Topics
Featured Products
Events
Solutions
Capabilities
Delivery Platforms
Our Methodology
Methodology & Participation
Reference Tools
Featured Events
S&P Global
S&P Global Offerings
S&P Global
Research & Insights
Solutions
Capabilities
Delivery Platforms
Our Methodology
Methodology & Participation
Reference Tools
Featured Events
S&P Global
S&P Global Offerings
S&P Global
Research & Insights
19 Jul 2023 | 13:01 UTC
Highlights
Only one Bugey unit may be restricted
Cattenom-2 set to return 23 days early
Aug contract bounces off two-year-low
EDF has updated the river temperature warning for its 3.6-GW Bugey nuclear power plant with only one unit potentially impacted from July 22, the French utility said July 19.
One of the four 900-MW units at Bugey was temporarily halted during the July 15/16 weekend due to environmental reasons, with river temperatures above a critical threshold for aquatic life.
"Due to the high temperatures forecasts on Rhone river, production restrictions are likely to affect Bugey nuclear production from July 22. However for grid constraints the production will be at least 1,800 MW and it may change according to the grid needs," EDF said in the updated transparency note with the first warning from July 10 canceled.
Last year, safety regulator ASN waived river temperature restrictions due to record-low reactor availability.
In June, the regulator noted a study showing little impact on aquatic life from the waiving of restrictions on four river-based nuclear power plants in Southern France.
Widespread negative hourly prices for the July 15/16 weekend across Northwestern Europe forced EDF to ramp down its fleet by up to 10 GW including Bugey 3.
Meanwhile, Bugey-2 is planned to come offline for a three-month annual maintenance stop on July 22.
On the flipside, EDF brought forward the restart of its 1.3-GW Cattenom-2 to July 19.
The unit has been offline since March and was due to return on Aug. 12, but was one of six 1.3-GW reactors for which EDF is performing checks and potential preventative repairs to stress corrosion issues faster than initially planned.
Nuclear output so far in July has averaged 32 GW, peaking July 19 above 34 GW.
Analysts at S&P Global Commodity Insights forecast French nuclear averaging around 30 GW in July and again in August.
French August baseload contracts rebounded July 19 above Eur75/MWh ($84/MWh) after settling July 17 at Eur71.74/MWh, a level not seen over two years for the contract, EEX data showed.
French reactor watchlist
Unit | (MW) | Outage start | Scheduled return | Notes |
Cattenom 2 | 1300 | 03/03/2023 | 19/07/2023 | Refueling, SIS check |
Gravelines 6 | 900 | 18/04/2023 | 26/07/2023 | Refueling |
Dampierre 4 | 900 | 31/05/2023 | 28/07/2023 | Refueling |
Cruas 4 | 900 | 28/05/2023 | 29/07/2023 | Refueling |
Saint Alban 1 | 1300 | 24/02/2023 | 30/07/2023 | Refueling, extra maintenance |
Gravelines 1 | 900 | 11/02/2023 | 01/08/2023 | Refueling, extra maintenance |
Paluel 3 | 1300 | 28/04/2023 | 03/08/2023 | Refueling |
Flamanville 1 | 1300 | 22/03/2022 | 13/08/2023 | Steam generator replacement |
Golfech 2 | 1300 | 27/03/2023 | 13/08/2023 | Refueling, SIS checks |
Golfech 1 | 1300 | 26/02/2022 | 20/08/2023 | 10-year-overhaul (SIS indication) |
Tricastin 3 | 900 | 15/07/2023 | 24/08/2023 | Refueling |
Chinon 3 | 900 | 02/05/2023 | 27/08/2023 | Refueling |
Bugey 2 | 900 | 22/07/2023 | 25/10/2023 | Refueling |
Source: EDF (compiled by S&P Global Commodity Insights from REMIT notes to July 19)