Register with us today

and in less than 60 seconds continue your access to:Latest news headlinesAnalytical topics and featuresCommodities videos, podcast & blogsSample market prices & dataSpecial reportsSubscriber notes & daily commodity email alerts

Already have an account?

Log in to register

Forgot Password

Please Note: Platts Market Center subscribers can only reset passwords via the Platts Market Center

Enter your Email ID below and we will send you an email with your password.


  • Email Address* Please enter email address.

If you are a premium subscriber, we are unable to send you your password for security reasons. Please contact the Client Services team.

If you are a Platts Market Center subscriber, to reset your password go to the Platts Market Center to reset your password.

In this list
Electric Power

BOEM grants two approvals for 12-MW Virginia offshore wind project

Energy | Electric Power | Metals | Non-Ferrous

Stationary storage market today and expectations for the future

Electric Power

Platts M2MS-Power

Commodities | Energy | Electric Power | Renewables | Banking | Infrastructure & Utilities

Financing US Power Conference, 21st Annual

Electric Power | Natural Gas | Natural Gas (North American)

Fitch releases stable outlook on US power, gas utilities sector for 2020

BOEM grants two approvals for 12-MW Virginia offshore wind project

Highlights

Facility Design Report, Fabrication and Installation Report received 'no objection'

Expected online in 2020, it would be the second US offshore wind plant

New York — With two important federal permits received Monday, the 12-MW Coastal Virginia Offshore Wind project being developed by Dominion Energy and Orsted US could start delivering power to the PJM Interconnection grid by summer 2020.

Not registered?

Receive daily email alerts, subscriber notes & personalize your experience.

Register Now

"This is a significant milestone as we move forward on building the first-ever fully permitted offshore wind project in federal waters," Mark Mitchell, Dominion Energy's vice president of generation construction, said in a statement.

Dominion received "no objection" determinations from the Bureau of Ocean Energy Management in response to its Facility Design Report and Fabrication and Installation Report. The reports were filed in conjunction with global developer Denmark-based Orsted and Spain's Siemens Gamesa Renewable Energy, the company manufacturing the project's two 6-MW wind turbines.

The FDR details the designs the project's major components and the FIR covers the equipment fabrication and installation plans. The companies said the BOEM approvals are needed to move forward with offshore construction, which is "on track for the summer of 2020."

INTERCONNECTION

Electrical contractor L.E. Myers Company began onshore construction in June to facilitate the wind turbine's interconnection at a Dominion-owned substation near Camp Pendleton, according to the statement.

The transmission project is listed as "under construction" in the PJM Interconnection queue, which also shows it has completed a Feasibility Study Report and Wholesale Market Participation Agreement for injection of 12 MW of energy and 1.5 MW of capacity.

The offshore wind turbines will connect onshore through a 23.5 nautical mile 34.5kV submarine cable, according to the WMPA.

Offshore wind generation projects today can enter the PJM queue and be studied under the current interconnection process and the projects are handled the same as any other technology.

However, PJM has had increasing interest from transmission developers seeking to build offshore transmission facilities for as-of-yet unplanned future wind generation and the grid operator is working to adjust its rules for that kind of development.

States along the US East Coast are seeking to procure more than 19,300 MW of offshore wind capacity through 2035, according to an analysis from S&P Global Market Intelligence and S&P Global Platts.

The country's only operational offshore wind farm is the 30-MW Block Island project in Rhode Island that started up in 2016 using GE's 6-MW Haliade turbines. The project was developed by Deepwater Wind, which Orsted acquired for $510 million in 2018.

Dominion has also filed an application with PJM to connect 2.6 GW of offshore wind to the mainland from 27 miles off the coast of Virginia Beach by 2026.

If approved, each project phase will total 880 MW, with the first phase being completed by 2024, according to Dominion.

-- Jared Anderson, jared.anderson@spglobal.com

-- Edited by Valarie Jackson, newsdesk@spglobal.com