11 Mar 2020 | 21:41 UTC — Houston

Analysis: MISO to add 4.25 GW of wind, 730 MW of gas capacity by mid-summer: report

Highlights

More than 2 GW of wind delayed from 2019

Projects totaling nearly 5 GW withdrawn

Houston — The Midcontinent Independent System Operator has 4,250 MW of wind and 730 MW of natural gas-fired generation under construction scheduled to be online by mid-summer, a Generation Interconnection Queue report generated Wednesday showed, and 28 projects, totaling almost 5 GW, have been withdrawn so far this year.

Of the wind total under construction, 2,032 MW has "Negotiated In Service Dates" in 2019, and when those projects will be brought online remains unclear, but likely by mid-summer or earlier.

Of the remaining wind total under construction, 1,116 MW is to be done by the end of April, while the remainder has negotiated in service dates in June.

Of the gas-fired generation under construction, a 25-MW combustion turbine being built in southern Mississippi's Cooperative Energy service area was originally slated to come online Jun 22, 2019, but no one from that organization responded immediately regarding when that project would achieve commercial operation.

The other gas project is a 705-MW combined-cycle gas turbine being build in St. Joseph County, Indiana, with a negotiated in service date of March 31, 2020.

Not counted in this gas-fired generation construction total is a 994-MW CCGT being built by Entergy in Westlake, Louisiana, which Entergy officials said "has always been expected to be in operation by mid-2020."

Another Entergy project slated for completion this summer is the 50-MW Capital Region Solar project "to be completed in the second quarter of this year," according to Entergy.

WITHDRAWN PROJECTS

Of the almost 5 GW of projects withdrawn through March 11, 1,322 MW had 2020 or earlier in-service dates, almost 2,126 MW was to come online in 2021, 729 MW was to come online in 2022, 125 MW was to come online in 2023 and one 670-MW gas-fired plant had a 2024 in-service date.

Planned wind capacity made up the lion's share of the withdrawn projects, totaling 1,825.6 MW, followed by solar with 1,645.2 MW, gas-fired with 1,476 MW and one battery project with a 25-MW capacity.

MISO has another 24 projects under construction with negotiated in-service dates during the second half of 2020, totaling 4,214 MW of capacity, led by 1,900 MW of wind, followed by 1,280 MW of solar and 924 MW of gas-fired capacity.

MISO generation under construction to be in-service by June 30, withdrawn through March 11
Under construction
State
Type
Capacity (MW)
On-line target month
Listed in-service date
IN
Wind
400.0
N/A
1-Apr-19
IL
Wind
202
N/A
1-May-19
IA
Hydro
55.0
N/A
31-May-19
MS
Natural gas
25.0
N/A
22-Jul-19
MN
Wind
200.0
N/A
13-Sep-19
IA
Wind
200.0
N/A
16-Sep-19
IA
Wind
200.0
N/A
28-Sep-19
IA
Wind
200.0
N/A
1-Oct-19
MI
Wind
80.0
N/A
1-Oct-19
SD
Wind
200.0
N/A
1-Oct-19
IL
Wind
150.0
N/A
1-Dec-19
SD
Wind
200.0
N/A
1-Dec-19
IN
Natural gas
705.0
March
31-Mar-20
IA
Wind
460.0
April
1-Apr-20
IL
Wind
202.4
April
23-Apr-20
IN
Wind
303.6
April
30-Apr-20
MN
Wind
150.0
April
30-Apr-20
SD
Wind
151.8
June
15-Jun-20
SD
Wind
300.0
June
29-Jun-20
LA
Solar
50.0
June
30-Jun-20
MI
Wind
400.2
June
30-Jun-20
MN
Wind
250.0
June
30-Jun-20
Projects withdrawn in 2020 through March 11
Number
Type
Capacity (MW)
On-line target year
State
1
Natural gas
50
2016
MN
1
Natural gas
702.0
2020
MI
1
Solar
120.0
2020
MO
3
Wind
450.0
2020
IA, IN, MI
7
Solar
900.2
2021
AR, IL, IN, MI, MO
7
Wind
1,225.6
2021
IL, IN, MI, MO
1
Natural gas
54.0
2022
IN
3
Solar
525.0
2022
LA, MI, MS
1
Wind
150.0
2022
MI
1
Battery
25.0
2023
AR
1
Solar
100.0
2023
AR
1
Natural gas
670.0
2024
MI
Note: Summer capacity is listed for natural gas and hydro.
Nameplate capacity is listed for battery, solar and wind.
Source: Midcontinent Independent System Operator