S&P Global Offerings
Featured Topics
Featured Products
Events
S&P Global Offerings
Featured Topics
Featured Products
Events
S&P Global Offerings
Featured Topics
Featured Products
Events
S&P Global Offerings
Featured Topics
Featured Products
Events
Solutions
Capabilities
Delivery Platforms
News & Research
Our Methodology
Methodology & Participation
Reference Tools
Featured Events
S&P Global
S&P Global Offerings
S&P Global
Research & Insights
Solutions
Capabilities
Delivery Platforms
News & Research
Our Methodology
Methodology & Participation
Reference Tools
Featured Events
S&P Global
S&P Global Offerings
S&P Global
Research & Insights
21 May 2021 | 20:07 UTC
A spate of heavy rain and bad weather impacted operations for power provider Entergy, impacting operations at both Motiva's and Total's Port Arthur, Texas, refineries.
PADD I (US ATLANTIC COAST)
PBF
Paulsboro, NJ
160,000
Partial shutdown
85,000
Q1 2021
NA
PBF
Delaware City, DE
182,200
Emissions
NA
1/17/2021
NA
Phillips 66
Linden, NJ
258,000
FCCU outage
145,000
5/4/2021
5/9/2021
PADD II (US MIDWEST)
BP-Husky (Cenovus)
Lima, OH
155,000
FCCU
55,000
1/1/2021
2/15/2021
Unidentified process unit upset
NA
3/23/2021
NA
CVR
Wynnewood, OK
74,500
Plant
57,500
Q2 2020
Q4 2021
RD hydrocracker conversion
26,500
Q2 2020
Q3 2021
Cold weather impact
NA
2/15/2021
NA
CVR
Coffeyville, KS
132,000
Process upset
NA
2/7/2021
NA
ExxonMobil
Joliet, IL
238,600
cogen offline
NA
2/7/2021
NA
HollyFrontier
Tulsa, OK
155,300
Cold weather impact
NA
2/15/2021
2/26/2021
HollyFrontier
Tulsa, OK East plant
70,300
Planned work
FCCU
2/9/2020
3/16/2021
Husky/Cenovus
Superior, WI
45,000
Heavy crude unit
25,000
4/26/2018
Q1 2023
Light crude unit
20,000
4/26/2018
2022
Meridian
Davis, ND
49,500
Plant
49,500
Q3 2023
Q1 2024
Marathon
Catlettsburg, KY
291,000
Cold weather impact
NA
2/15/2021
NA
Marathon
St. Paul Park, MN
103,000
SRU
NA
4/1/2021
4/30/2021
PBF Energy
Toledo, OH
172,800
Planned work reformer
51,800
2/15/2021
3/12/2021
Planned work crude cuts
86,000
Phillips 66
Ponca City, OK
207,000
FCCU regenerator
76,912
2/8/2021
2/28/2021
Cold weather impact
NA
2/15/2021
2/28/2021
Valero
Ardmore, OK
86,000
Plant
NA
12/30/2020
2/3/2021
FCCU power outage
30,000
2/3/2021
2/23/2021
Alkylation unit startup
NA
NA
3/20/2021
WRB
Wood River, IL
356,000
2 units upset
NA
2/7/2021
NA
Cold weather impact
2/14/2021
NA
PADD III (US GULF COAST)
Calcasieu Refining
Lake Charles, LA
135,000
Idled
135,000
8/1/2020
NA
Calumet Specialty
Cotton Valley, LA
13,020
Cold weather impact
13,020
2/15/2021
2/25/2021
Calumet Specialty
Shreveport, LA
57,000
Cold weather impact t/a delayed
2/1/2021
3/15/2021
Calumet Specialty
Princeton, LA
83,000
Cold weather impact
83,000
2/15/2021
2/25/2021
Chevron
Pasadena, TX
112,229
Cold weather impact
NA
2/15/2021
3/11/2021
FCCU startup
52,000
5/7/2021
5/11/2021
Citgo
Corpus Christi, TX
167,500
Cold weather impact
NA
2/15/2021
3/4/2021
FCCU feed loss due to rain
83,800
5/19/2021
5/19/2021
FCCU work
83,800
1/15/2021
2/11/2021
Cold weather impact
NA
2/14/2021
NA
rate cut on Colonial shutdown
NA
5/10/2021
NA
Deer Park
Deer Park TX
318,000
FCCU work
75,000
1/3/2021
2/12/2021
Cold weather impact
2/14/2021
3/12/2021
CDU valve snag
NA
3/29/2021
NA
CDU snag
NA
3/31/2021
3/31/2021
Delek US
Big Spring, TX
73,000
FCCU work
23,500
3/3/2021
NA
SRU #2
NA
3/10/2021
NA
DHT issue/rate cuts
24,000
3/14/2021
NA
DHT process trip
24,000
5/17/2021
5/17/2021
Delek US
Krotz Springs, LA
80,000
Partial shutdown
60,000
11/15/2020
Q1 2021
Restart after turnaround
11/15/2020
3/31/2021
Delek US
Tyler, TX
75,000
FCCU
20,250
3/10/2021
NA
Cold weather impact
NA
2/15/2021
NA
FCCU trip
20,250
5/7/2021
5/7/2021
Delek US
El Dorado, AK
83,000
Cold weather impact t/a moved up
83,000
2/15/2021
3/15/2021
Planned work
4/1/2021
4/30/2021
ExxonMobil
Baytown, TX
560,500
Cold weather impact
NA
2/15/2021
3/5/2021
ExxonMobil
Beaumont, TX
369,024
Cold weather impact
NA
2/15/2021
NA
Hole in coker unit pipe
2/20/2021
NA
Flint Hills
Corpus Christi, TX
338,500
Cold weather impact
NA
2/15/2020
3/4/2021
Product pipeline leak
NA
3/11/2021
3/11/2021
Lyondell Basell
Houston, TX
263,776
CDU shutdown
NA
2/12/2021
2/25/2021
Cold weather impact
2/15/2021
3/4/2021
Marathon
Gallup, NM
27,000
Shut down
27,000
Q2 2020
NA
Marathon
El Paso, TX
131,000
Cold weather impact
NA
2/15/2021
NA
FCCU trip/reduced rates
35,000
5/18/2021
NA
Marathon
Galveston Bay, TX
585,000
planned work
NA
Q1 2021
Q1 2021
Cold weather impact
NA
2/15/2021
3/7/2021
FCCU
NA
3/25/2021
3/25/2021
FCCU3 blower trip
NA
4/9/2021
4/9/2021
Ultraformer
NA
4/18/2021
4/18/2021
coker compressor trip
NA
5/20/2021
5/20/2021
Motiva
Port Arthur, TX
607,000
Cold weather impact
NA
2/15/2021
3/11/2021
Delayed Coker
NA
3/18/2021
3/19/2021
DCU/reformer weather shutdown
NA
5/17/2021
5/17/2021
Phillips 66
Sweeny, TX
265,000
Cold weather impact
NA
1/31/2021
NA
265,000
Delayed Coker
78,700
4/3/2021
NA
Delayed Coker
78,700
5/7/2021
5/7/2021
Phillips 66
Belle Chasse, LA
255,600
Plant
NA
8/23/2020
1/14/2021
San Antonio Refinery
San Antonio, TX
20,000
Cold weather impact
NA
2/15/2021
NA
Shell
Convent, LA
211,146
Permanent shut down
211,146
11/15/2020
NA
Shell
Norco, LA
227,400
Flaring/catalyst
NA
1/28/2021
NA
Total S.A.
Port Arthur, TX
225,500
Cold weather impact
NA
2/15/2021
3/16/2021
Planned start-up of FCCU
80,000
3/14/2021
3/14/2021
FCCU feed cut
80,000
3/26/2021
4/9/2021
Refinery wide power dip
NA
5/17/2021
5/17/2021
Valero
Houston, TX
205,000
FCCU upset
NA
1/8/2021
1/9/2021
Cold weather impact
NA
2/15/2021
NA
Valero
Corpus Christi, TX
290,000
Reformer shut
NA
2/9/2021
NA
Cold weather impact
NA
2/15/2021
2/28/2021
HCU repairs
51,000
3/11/2021
NA
Reformer repair
39,000
3/27/2021
NA
Valero
McKee, TX
195,000
Cold weather impact
NA
2/15/2021
NA
Valero
Texas City, TX
225,000
Cold weather impact
NA
2/15/2021
NA
Valero
Port Arthur, TX
335,000
Cold weather impact
NA
2/15/2021
NA
Valero
Three Rivers, TX
89,000
#1 SRU
NA
3/18/2021
NA
WRB
Borger, TX
146,000
FCCU
56,000
2/14/2021
NA
Cold weather impact
NA
2/15/2021
NA
FCCU snag
NA
3/9/2021
3/26/2021
Plant-wide power outage
NA
5/5/2021
5/9/2021
PADD IV (US ROCKIES)
HollyFrontier
Cheyenne, WY
48,000
Repurposed
48,000
8/1/2020
NA
Chevron
Salt Lake City, UT
54,720
Flaring
NA
2/1/2021
NA
Calumet
Great Falls, MT
25,000
RD co-process 12,000
12,000
Q1 2022
Q1 2023
Suncor
Commerce City, CO
103,000
Planned FCCU work
30,500
4/15/2021
5/5/2021
PADD V (US WEST COAST)
BP
Cherry Point, WA
242,000
Planned unit shutdown
NA
2/24/2021
3/3/2021
Chevron
El Segundo, CA
269,000
NA
73,800
2/9/2021
NA
alkylation unit
33,300
5/16/2021
NA
fire cat feed hydrotreater
NA
5/14/2021
NA
Marathon Petroleum
Carson, CA
363,000
Planned flaring
NA
5/22/2021
5/27/2021
Marathon Petroleum
Martinez, CA
161,000
Repurposed
161,000
Q2 2020
NA
Marathon Petroleum
Anacortes, WA
119,000
Planned work FCCU
51,500
2/3/2021
2/14/2021
PBF
Torrance, CA
160,000
Planned work
NA
H2 2021
H2 2021
Planned work
NA
3/1/2021
NA
PBF
Martinez, CA
156,400
Planned work
NA
H2 2021
H2 2021
Par Pacific Holdings
Honolulu, HA
148,000
Partial shutdown
54,000
Q3 2020
NA
Par Pacific Holdings
Tacoma, WA
40,700
NA
NA
Q1 2021
Q1 2020
Phillips 66
Rodeo, CA
120,200
Repurposed
120,200
2020
2024
Phillips 66
Santa Maria, CA
44,500
To be shut down
44,500
2023
2023
Shell
Anacortes, WA
145,000
CRU trip
21,700
1/13/2021
NA
FCCU upset
57,900
1/12/2021
NA
FCCU trip
57,900
2/4/2021
NA
restart of DCU, HTU and SRU
3/7/2021
4/28/2021
Valero
Wilmington, CA
85,000
SRU upset
NA
3/6/2021
NA
US VIRGIN ISLANDS
Limetree Bay
St. Croix, USVI
176,400
restart
172,400
1/15/2021
NA
EPA-ordered 60 day shutdown
5/14/2021
7/4/2021
CANADA
Parkland
Burnaby, BC
55,000
small maintenance project
NA
12/1/2021
12/31/2021
North Atlantic Refining
Come by Chance, NF
130,000
Warm idle mode
130,000
3/29/2020
NA
Suncor
Edmonton, AB
142,000
Expansion
146,250
Q4 2020
Q12021
Planned work
Q2 2021
Q22021
Suncor
Montreal, QC
137,000
Planned work
137,000
3/26/2021
5/14/2021
MEXICO
Pemex
Minatitlan
285,000
fire in gasoline unit
NA
4/7/2021
7/6/2021