PremierAfrican Minerals Ltd. said July 18 that screens, plant and electricalreticulation works have been completed at its 49%-owned tungsten project inZimbabwe.
The plant is now undergoing phased commissioning andoptimization to achieve the anticipated recoveries and operational throughput.
Wolframite concentrate from ore from the underground mine hasbeen produced. The throughput will be steadily increased to the plant's designcapacity of 16 tonnes per hour.