Norway's Sverdrup Phase 2 oil output restart delayed after power failure

Energy | Oil | Crude Oil

Platts Crude Oil Marketwire

Commodities | Energy | Oil | Crude Oil | Energy Transition

At Asia’s APPEC, energy transition and Russia steal the limelight

Oil | Energy Transition | Energy

APPEC 2024

Energy | Natural Gas | LNG | Energy Transition | Emissions

Biden directive pushes wider use of climate cost metric in US agency actions

Energy | Oil | Crude Oil

Dated Brent Price Assessment

Agriculture | Energy | Energy Transition | Petrochemicals | Oil | Sugar | Biofuels | Renewables | Hydrogen | Emissions | Carbon | Aromatics | Olefins | Refined Products | Jet Fuel | Crude Oil | Naphtha | Polymers

Bionaphtha for plastics: a building block towards sustainability

For full access to real-time updates, breaking news, analysis, pricing and data visualization subscribe today.

Subscribe Now

Norway's Sverdrup Phase 2 oil output restart delayed after power failure

Highlights

Power to facilities restored, but startup hits technical glitch

Delay follows earlier loading deferrals

  • Author
  • Nick Coleman
  • Editor
  • Alisdair Bowles
  • Commodity
  • Energy Transition Oil

Production at Norway's flagship Johan Sverdrup oil project remained at a reduced rate of 535,000 b/d on Jan. 16 as an equipment fault hampered recovery from a power failure at recently commissioned Phase 2 facilities, a spokesperson for state-controlled Equinor said.

Not registered?

Receive daily email alerts, subscriber notes & personalize your experience.

Register Now

Following the Jan. 11 power failure the core Phase 1 facilities quickly restarted and "produce a stable 535,000 b/d," the spokesperson told S&P Global Commodity Insights.

Power supply was then restored on Jan. 13 at the Phase 2 facilities, which were first put into operation in mid-December. However, the restart of production at the Phase 2 process platform is "delayed due to an equipment fault that occurred when starting after a couple of days from a cold platform," the spokesperson said. "Repair work has started."

The Phase 2 facilities are expected to raise overall Sverdrup crude capacity to a plateau of 720,000 b/d, with possible increases above that level. Prices for the medium sour grade have been supported of late by sanctions against Russia and curbs on buying Russia's Urals.

Sverdrup crude was assessed at a $1.5/b discount to North Sea benchmark Dated Brent on Jan. 13, unchanged on the day, by Platts, which is part of S&P Global Commodity Insights.

Equinor on Jan. 14 revised its loading schedule for January for Sverdrup, pushing some cargoes into February.

The Sverdrup project, which first came on stream in 2019, relies on renewable power from the mainland, sent offshore through a 200 km subsea cable, part of Norway's efforts to lower emissions. It has also served as a catalyst for bringing low-carbon power supply to other nearby facilities.