立即注册,

不到 60 秒您即可继续访问:最新资讯提要分析主题和专题大宗商品视频、播客和博客样本市场价格和数据专题报道订阅用户通知和每日大宗商品电子邮件提醒

已有帐户?

登录以注册

忘记密码

请注意:Platts Market Center 订阅用户只能通过 Platts Market Center 重置密码

请在下面输入您的电子邮件 ID,我们将给您发送一封包含您密码的电子邮件。


  • 电子邮件地址* 请输入电子邮件地址。

如果您是高级订阅用户,出于安全原因,我们无法向您发送您的密码。请联系客服团队

如果您是 Platts Market Center 订阅用户,若要重置密码,请转到 Platts Market Center 重置您的密码。

在此列表中
液化天然气 (LNG) | 天然气

Cameron LNG seeks authorization to ship commissioning cargoes

液化天然气 (LNG) | 天然气凝液 (NGL)

Platts LP Gaswire

大宗商品 | 能源 | 电力 | 排放物 | 可再生能源 | 天然气 | 天然气(北美)

northeast-power-and-gas-markets

天然气 | 石油 | 原油

APPEC:业内专家表示,布伦特价格前景因市场不确定性和波动而蒙上阴影

Cameron LNG seeks authorization to ship commissioning cargoes

亮点

Production is expected to start within days

Sempra prepares for site visit by President Trump

Houston — As it prepares to start production of its first liquefaction train, Sempra Energy's Cameron LNG is asking US regulators for permission to ship its planned commissioning cargoes on a specified schedule.

尚未注册?

接收每日电子邮件提醒、订阅用户通知并获得个性化体验。

立即注册

The operator said in February that it planned to export as many as seven commissioning cargoes, depending on customer needs, before commercial service under long-term contracts begins. It said at the time that gas marketer Tenaska would arrange the feedgas supply needed for commissioning.

Production is expected to begin within days. In a letter to the Federal Energy Regulatory Commission on Thursday, Project Director Jamie Gray asked for authorization by May 16 to start shipping commissioning cargoes. The schedule of expected commissioning deliveries was filed under seal, and Sempra has not said where it expects its first export to land.

"With the first production of LNG from Train 1, Cameron LNG will file weekly commissioning reports as requested by the commission," Gray said.

The $10 billion project -- a joint venture of affiliates of San Diego-based Sempra, France's Total, Japan's Mitsui and a company jointly owned by Japan's Mitsubishi and NYK -- faced delays in late 2017 and early 2018. Startup has been highly anticipated by the market, and the two contractors added workers at the site to get things back on track, One of those contractors, McDermott, recently said that startup of trains 2 and 3 will be delayed until 2020.

President Donald Trump has scheduled a visit to the site on Tuesday, and that appearance could coincide with first LNG production.

It's not clear how long it will take once production starts for Cameron LNG to have enough LNG to ship its first cargo. It has said it would be able to move somewhat quicker than some of its peers because its storage tanks already had a sizable amount of LNG in them that was left over from when the facility was an active receiving terminal a decade ago.

Sempra has also proposed adding liquefaction facilities in Port Arthur, Texas, and Baja California, Mexico, as part of an ultimate goal of supplying up to 45 million mt/year of LNG to markets in Latin America, Asia, Europe and the Middle East.

Sempra is targeting a late 2019 final investment decision for the Mexico project and a late 2019 or early 2020 FID for Port Arthur LNG. US regulators recently granted a permit certificate to the Texas project, as well as the right to export cargoes to countries with which the US does not have a free-trade agreement.

-- Harry Weber, Harry.Weber@spglobal.com

-- Edited by Gail Roberts, newsdesk@spglobal.com