Tauron's 450-MW Polish gas plant synchronized after coronavirus delay

원자재 | 에너지 | 천연가스

Platts European Gas Daily

Tauron's 450-MW Polish gas plant synchronized after coronavirus delay

하이라이트

Stalowa Wola CCGT starts testing phase

$403 million JV between Tauron, PGNiG

Project initially due to commission in 2016

Warsaw — Polish state-controlled utility Tauron said Aug. 24 it had completed the synchronization of its much-delayed, 450-MW Stalowa Wola combined cycle gas turbine with the national grid.

아직 가입하지 않으셨나요?

일일 이메일 알림과 구독자 노트를 받고 이용 경험을 내게 맞게 설정하세요.

지금 가입하세요

"Synchronization of the gas steam turbine set completes the investment," Tauron CEO Wojciech Ignacok said. "The unit will now go through the optimization, tuning and testing phase," he said.

The Zloty 1.5 billion ($402.8 million) joint venture investment between Tauron and state gas company PGNiG, was built to replace old coal-fired capacity at Tauron's Stalowa Wola plant in south eastern Poland.

It was due to be commissioned in the second quarter, but was delayed by the coronavirus pandemic. The unit will supply electricity to the national grid and heat to the residents of Stalowa Wola and surrounding areas. The project will emit around 360 kg of CO2 per MWh, Tauron said.

The CHP was originally scheduled to be ready in mid-2016, but Tauron canceled the contract with the constructor, Abener Energia, saying the Spanish company had failed to meet deadlines, when the investment was 85% complete. The unit was completed by a consortium of Polish companies led by Energopomiar.