Sellindge evacuated after fire at UK-France IFA interconnector site

Commodities | Electric Power | Electricity | Energy | Energy Transition | LNG | Natural Gas | Natural Gas (European) | Oil | Crude Oil | Refined Products | Fuel Oil | Gasoline | Metals | Non-Ferrous | Steel | Petrochemicals | Polymers

Market Movers Europe, Sept 27-Oct 1: Panic-buying hits UK petrol stations, as Europe deals with energy crisis

Energy | Electric Power

Platts Forward Curves – Gas and Power

Metals | Coronavirus | Steel

16th Steel Markets Asia Conference

Energy | Coal | Electric Power | Oil | Petrochemicals | Natural Gas | Energy Transition | Metals | Emissions | Electricity | Crude Oil | Renewables | Steel | Steel Raw Materials | Nuclear

China's Guangdong to ban new coal-fired power plants and plant expansions

Commodities | Energy | Natural Gas | Natural Gas (European) | Natural Gas Risk

Time for Europe and the IEA to create a strategic gas reserve

Sellindge evacuated after fire at UK-France IFA interconnector site

Highlights

2-GW link flows at zero

Emergency services in attendance

1-GW IFA pole was on outage

A fire at National Grid's IFA power interconnector site in Sellindge has caused the site to be evacuated while emergency services deal with the incident, the UK transmission system operator said Sept. 15.

Not registered?

Receive daily email alerts, subscriber notes & personalize your experience.

Register Now

The IFA link offers 2 GW of capacity and has been importing power in recent days due to high UK price premiums.

"The site has been evacuated and the safety of our staff, emergency teams and local residents is our highest priority," National Grid said in a tweet.

Further updates would be made in due course, it said.

National Grid ESO said it was still forecasting sufficient margin for this evening's peak demand period.

It noted that one pole of the 2-GW IFA link had been on outage, reducing availability to 1 GW.

Maintenance on the pole changed from "planned" to "unplanned failure" early Sept. 15 on French system operator RTE's transparency website.

RTE gave an estimated end date of the work as Oct. 13, with daily variations in net transmission capacity until then.

Interconnector flows on the asset were at zero on Elexon's data summary webpage.

Flows on the IFA2 link to France were seen at 1 GW, as were flows on the NEMO link to Belgium, while those on the BritNed link to the Netherlands were at 500 MW.

Hourly UK day-ahead power prices on the N2EX exchange rose to GBP2,500.01/MWh ($3,460.14/MWh) for delivery between 19:00-20:00 Sept. 15.

S&P Global Platts assessed the price of UK day-ahead baseload power at GBP385.00/MWh for delivery Sept. 15. Front-month October base power was assessed at GBP158.65/MWh, up 12.20% on the day.