First Graphene Ltd. on Feb. 26 reported initial production at its commercial graphene production facility in Henderson, Western Australia.

The facility will have an initial capacity of up to 25 tonnes per year, based on a single-shift operation five days per week. Estimated full production capacity is 90 tonnes per year.

The company said it met its A$1 million budget for the construction of the site, which was granted approval in July 2017.